November 5, 2026
Since the ribbon was cut in January 2025, the paved Bayview Trail at West Lake Park has run north from 20th Street SE and stopped at 12th Street SE. For now the barricades are on the street. 12th Street SE between 87th Avenue SE and 89th Avenue SE has been closed to cars since October 26, and the City of Lake Stevens lists November 13 as a tentative reopening date. Crews are replacing the sidewalk there with a 10-foot multi-use path. That path will carry the trail across 12th Street and into its next segment, which runs north to 8th Street SE.
The fencing looks like ordinary roadwork. It's actually the first construction on the long section of the trail. That section is meant to reach Marysville eventually, and the price of each later piece explains why it will arrive in stages.
The city's road closure notice describes the work this way. Crews are removing the existing sidewalk and putting in a 10-foot multi-use path. The path connects the current Bayview Trail at West Lake Park to the next phase, which extends the 10-foot-wide paved trail from 12th Street SE to 8th Street SE.
If you walk, run, or drive near West Lake Park this week, these are the details that matter:
When this post goes up on November 5, the closure will be about halfway through its posted window. The November 13 date is tentative, so check the project page before the following weekend.
The closure is the visible part of a job that started earlier. The project page posted an update on September 14 saying construction was underway. Crews began with the pedestrian ramp connection, sidewalk removal and replacement, and a road realignment.
The realignment is written into the project's scope. In the city's 2026–2031 Capital Improvement Plan, the line for Phase 0.5 reads "12th St to 8th St trail, realign 12th Street and connect to Phase 0 project." Moving the trail across a road takes more than a crosswalk. The street has to be reshaped for the path, and that is why cars are detoured while people on foot still get through.
The design work is done. Perteet, Inc. is the design engineer, and the city has posted 100% construction plans for the phase on the project page. The page describes the new segment from 12th Street SE to 8th Street SE as a 10-foot-wide paved trail.
On its own, 8th Street SE is a modest goal. It matters because of where the trail is ultimately headed. The Everett Herald reported at the January 2025 ribbon-cutting that Lake Stevens and Marysville are jointly building a 4.7-mile paved path. It will run from the south end of Marysville's existing Bayview Trail at 64th Street NE down to 20th Street SE in Lake Stevens. The section that opened that day, Phase 0, covers 20th Street SE to 12th Street SE. The Herald also reported that the route runs beneath power lines owned by Bonneville Power Administration and Seattle City Light, and that both granted the two cities easements to build it.
The 4.7 miles covers the full connector between the two cities. The capital plan splits the Lake Stevens side into phases, and each phase has its own price:
Phase | Segment | Total project cost in the 2026–2031 CIP |
|---|---|---|
Phase 0.5 | 12th St SE to 8th St SE, with 12th Street realignment | $1,546,000 |
Phase 1 | 8th St SE to SR 204 | $3,470,000 |
Phase 2 | SR 204 to 17th St NE | $2,800,000 |
Phase 3 | 17th St NE to Soper Hill Rd | $5,100,000 |
Phase 4 | 20th St & 83rd Ave NE to the Marysville connection | $1,700,000 |
The plan lists about $14.6 million across those five phases. The phase under construction now accounts for roughly a tenth of that. The phase to Soper Hill Road is the most expensive at $5.1 million, more than three times the cost of the current work. The plan describes Phases 1 through 3 as coordinated with the City of Marysville. In other words, the sections that bring the trail closer to Marysville also bring in a second city's schedule.
The 8th Street SE connection is the first step on that longer route. When it opens, the trail at West Lake Park will lead somewhere new instead of ending at a curb. The table also explains why each step beyond it will take its own round of funding.
So far the trail has been paid for piece by piece, mostly with state dollars. The Herald reported that a $504,700 state grant funded the connector's design to 30% completion. In January 2025, the two cities said they would request another $600,000 in the following legislative session. Later that year, Parks and Recreation Planning Board minutes from July 14, 2025 recorded that Lake Stevens received $500,000 from the state budget to plan the next phase of the Bayview Trail.
The two-city partnership is part of how that money gets won. Brett Gailey, then the mayor of Lake Stevens, put it this way to the Herald at the ribbon-cutting: "When we can go hand-in-hand and do regional projects together with multiple cities, it makes it easier for legislators to provide that money. Because it doesn't just serve Lake Stevens, it serves a much broader community."
The planning for the next segment is already public. On June 3, 2026, the cities held an open house at the Marysville Civic Center, 501 Delta Ave., where residents could review the design for extending Marysville's Bayview Trail south to Lake Stevens. Lake Stevens filed it under Bayview Trail Phase I. The city's open house page also links to a comment page for the project.
Each phase follows the same sequence: plan, design, fund, build. Phase 0.5 is the first to reach the build step since the January 2025 ribbon-cutting. Phase 1 has had planning money and a public design review. Phases 2 through 4 are line items in the capital plan.
The construction sits at the trail's southern anchor, so the park itself is worth a look. The West Lake Dog Park opened to the public on June 25, 2025. The Parks Board minutes describe "an eager group of dogs with their 2-legged companions" and note that new ADA-accessible bench pads were added.
The city also has plans for the park beyond the trail. The capital plan lists West Lake Park Recreation Amenities at $100,000, described as planning amenities "consistent with the powerline easements." Possible options it names include revamping the sports field, adding a playground, or building a pump track. The same line cites Snohomish County's Capital Improvement Program. The power lines that set the trail's route also limit what the park around it can become.
Until November 13, or whenever the city lifts the closure, the paved trail between 20th Street SE and the work zone stays as it has been since January 2025, and people on foot can still get through at 12th Street SE. Updates are posted on the Bayview Trail Phase 0.5 project page, where the September and October notices first appeared.
Trail projects like this one shape how a part of town feels day to day, and I follow them as closely as any sale. If you'd like to talk through how the Bayview Trail's progress affects the area around West Lake Park, or what's ahead for your own street, Carrie Pearson is glad to help. Schedule a Strategy Call.
Real estate is built on trust and it is more than buying and selling homes, it's about having an experienced professional in your corner who can anticipate challenges, solve problems, and guide you with confidence. With over 23 years of experience, extensive market knowledge, expert negotiation skills and a genuine commitment to her clients, Carrie is known for working tirelessly to make the process as smooth and successful as possible. Whether you're buying, selling, investing, or simply exploring your options in Snohomish County, King County or the Greater Seattle Area, Carrie is dedicated to protecting your interests, providing honest advice, and delivering results every step of the way.